Guide 01 · 5 min read
Remodeling a Kitchen in an HOA in Scottsdale
A kitchen remodel in an HOA community can need two approvals: the City of Scottsdale permit, and the association's design review. The city does not care what your CC&Rs say, and the association can still say no after the permit is issued. Most Scottsdale kitchens sit inside an association, from McCormick Ranch to DC Ranch to the condo towers near Kierland.
01Good to know
What does the City of Scottsdale require for a kitchen remodel?
The city splits work into three buckets: no permit, a minimum permit for a single trade, and a full permit for structural or multi-trade work. Cosmetic work such as interior doors, hardware, flooring, trim, drywall, paneling, and stucco does not need a permit, per the city's home improvement guidance (City of Scottsdale Home Improvement (opens in a new tab)).
| Work | City requirement |
|---|---|
| Paint, hardware, flooring, trim, interior doors, drywall | No permit |
| Replace a plumbing fixture in the same location | Minimum plumbing permit |
| Add or alter an electrical circuit | Minimum electrical permit |
| Add or replace windows, except glass only in an existing frame | Minimum window and door permit |
| Replace AC or air handler, like for like | Minimum mechanical permit |
| Move plumbing, gas, walls, or multiple systems | Full permit with plan review |
Source: A.R.S. 33-1817 (opens in a new tab)
Permit requests run through the city's SPUR portal, and single-family remodels go through residential plan review rather than the hearing process used for commercial work (City of Scottsdale Permit Services (opens in a new tab), Residential Plan Review (opens in a new tab)).
02Permits
What can the HOA still block after the city approves?
Anything the CC&Rs and design guidelines cover, which in a kitchen remodel usually means the parts visible from outside. The city's own page says it plainly: subdivision covenants, conditions and restrictions may govern some items even though they are not regulated by the city, so check with the association before proceeding (City of Scottsdale (opens in a new tab)).
The usual triggers in a kitchen project:
- A new or enlarged window, or a change in window frame color
- A patio door or slider replacement
- A range hood ducted through the roof or the exterior wall
- Any change to stucco, paint, or exterior trim
- A new vent, skylight, or exterior penetration
- Construction access, dumpster placement, and work hours
Purely interior work with no exterior change often still needs a design review submittal, because many Scottsdale associations require notice before any construction. Read the CC&R section on alterations before assuming a kitchen is "interior only".

03Good to know
What does Arizona law say about the design committee?
Arizona's Planned Communities Act regulates how design and architectural committees work. Under A.R.S. 33-1817, membership on a design review committee must include at least one member of the board of directors, who serves as committee chairperson (A.R.S. 33-1817 (opens in a new tab)).
The same statute sets a formal process for new construction or a rebuild of the main residence, including a final design approval meeting the owner may attend, at least two on-site formal reviews during construction, written reports within 5 business days after each review, and a written report within 30 business days after the second review. A kitchen remodel is not new construction, so that formal track usually does not apply. The lesson still applies: ask for written approval, and ask what gets inspected during the work.
046 steps
What should be in the submittal packet?
One packet, sent once, with everything the committee needs. Missing one item is how a project loses two weeks.

The plan set you are submitting to the city, including any exterior elevations
A site plan showing the dumpster or staging location if exterior access changes
Material and finish samples
door style, counter material, backsplash, paint or stucco color if visible
Exterior change details
window spec, hood termination, vent location
Contractor information
license number, insurance certificate, and the work hours proposed
The approval request form from the association, signed
Ask for a written response with a date. Verbal approval from a committee member is not approval.
056 steps
What is the order of operations?
City permit and HOA review can run in parallel, and the sequence that avoids rework is this:

Read the CC&Rs and design guidelines first, before design is finished
Get the association's submittal requirements and meeting calendar
Design to both sets of rules at once, so the drawings do not need a second pass
Submit to the city through SPUR, and to the association in the same week
Order nothing that is custom and non-returnable until both are approved in writing
Keep the approved set, stamped, on site during construction
Step 5 is the expensive one. Cabinets ordered before approval are the most common sunk cost in an HOA kitchen.
06Good to know
What gets denied, and why?
Four denial reasons cover most of them: an exterior change nobody mentioned in the submittal, a material that is not on the approved palette, a work window outside the association's allowed hours, and an incomplete packet that the committee cannot evaluate.
Most denials are not philosophical. They are paperwork. A submittal that shows the exterior change, names the material, and states the hours passes more often than one that argues about design taste.
Our kitchen remodeling page shows what a full project involves once both approvals are in place.

075 questions
Questions people ask
Still have a question? Call (480) 672-2248 and describe the kitchen.
01Do I need HOA approval for an interior kitchen remodel in Scottsdale?
Often yes, at least a notice or a submittal, because many associations require approval before construction starts. Read the alterations section of your CC&Rs rather than assuming interior work is exempt.
02Can my HOA stop a remodel the city already permitted?
The association enforces the CC&Rs, which are a private contract, and the city permit does not override them. That is why both approvals are needed before work starts.
03How long does HOA approval take?
It depends on the association's meeting schedule and completeness of the packet, since many committees review at scheduled meetings. Ask the manager for the calendar and the current submittal deadline before you plan a start date.
04What if the previous owner made changes without approval?
Disclose it and ask the association how to resolve it, because unapproved alterations usually have to be corrected or retroactively approved, and that can surface at sale.
05Does the design committee have to include a board member?
Yes. Under A.R.S. 33-1817 the committee must include at least one board member, who chairs it. (A.R.S. 33-1817 (opens in a new tab))
08How it works
Next step
Find the alterations section of your CC&Rs and the design guidelines, and note the submittal deadline for the next committee meeting. Those two dates decide whether this kitchen starts this quarter or next.
09Keep reading
- Kitchen remodel permits in Scottsdale: the city side in full.
- Kitchen remodel timeline: where review sits in the schedule.
- Planning a kitchen remodel: the sequence before demolition.
- Service areas: the neighborhoods we work in.
- Contact: to set up an on-site assessment.
- Kitchen Island vs Peninsula in Scottsdale:
- Cabinet Refacing vs Replacement in Scottsdale: